Updates – Azizi Yasamine

June 2015

  • Concrete casting of 8th floor slab COMPLETED 100%
  • Mechanical, electrical and plumbing works of 8th slab 100% COMPLETED
  • Shuttering work for 9th slab 70% COMPLETED
  • Steel fixing of vertical structure of 9th slab 100% COMPLETED
  • Pouring concrete for vertical structure of 9th slab 100% COMPLETED
  • Block work for 5th floor completed 60%
  • Plaster work for 2nd floor 20%


May 2015

  • Shuttering work for 7th slab
  • Steel fixing for 7th slab
  • Post tensioning works for 7th slab
  • Concrete pouring of 7th slab
  • Mechanical, electrical and plumbing works of 8th slab
  • Steel fixing of vertical structure for first part of 8th slab
  • Pouring concrete for vertical structure for first part of 8th slab


April 2015

  • Shuttering work for 5th slab 100% COMPLETED
  • Steel fixing for 5th slab 100% COMPLETED
  • Post tensioning works for 5th slab 100% COMPLETED
  • Concrete pouring of 5th slab 100% COMPLETED
  • Mechanical, electrical and plumbing works of 5th slab 100% COMPLETED
  • Steel fixing of vertical structure for first part of 6th slab 100% COMPLETED
  • Pouring concrete for vertical structure for first part of 6th slab 100% COMPLETED

March 2015

  • Shuttering work for 4th slab
  • Steel fixing for 4th slab
  • Post tensioning works for 4th slab
  • Concrete pouring of 4th slab
  • Mechanical, electrical and plumbing works of 4th slab
  • Steel fixing of vertical structure for first part of 5th slab
  • Pouring concrete for vertical structure for first part of 5th slab

February 2015

  • Concrete pouring of 2nd slab including swimming pool
  • Steel fixing and shuttering of columns, shear walls and core walls of 2nd floor
  • Concrete pouring of columns, shear walls and core walls of 2nd floor
  • Scaffolding and shuttering of 3rd slab
  • Steel fixing of 3rd slab
  • Mechanical, electrical and plumbing works of 3rd slab

January 2015

  • Steel Reinforcement and shuttering of first floor columns and shear walls.
  • Concrete pouring of first floor columns and shear walls.
  • Scaffolding and shuttering of second slab (Area of slab is about 3800 m2).
  • Steel fixing of first slab.
  • Post-tensioning works of first slab.
  • Mechanical, electrical and plumbing works of fist slab.
  • Scaffolding and shuttering of swimming pool body at second floor.
  • Steel fixing of swimming pool body at second floor.