Azizi Orchid

Azizi Orchid


Azizi Orchid at Al Furjan Dubai by Azizi Developments

Updates – Azizi Orchid

June 2015

  • Concrete casting of 5th floor slab completed 100%
  • Mechanical, electrical and plumbing works 5th slab 100% COMPLETED
  • Steel Fixing of 6th slab100% COMPLETED
  • Post tensioning works of 6th slab 100% COMPLETED
  • Block work for 3rd floor completed 30%
  • Plaster work for 2nd floor completed 70%


May 2015

  • Steel Fixing of 3rd slab
  • Post tensioning works of 3rd slab
  • Mechanical, electrical and plumbing works 3rd slab
  • Concrete Pouring of 3rd slab
  • Steel fixing of vertical structure for first part of 4th slab
  • Pouring concrete for vertical structure for first part of 4th slab


April 2015

  • Steel Fixing of 2nd slab 100% COMPLETED
  • Post tensioning works of 2nd slab 100% COMPLETED
  • Mechanical, electrical and plumbing works 1st slab 100% COMPLETED
  • Concrete Pouring of 2nd slab 100% COMPLETED
  • Steel fixing of vertical structure for first part of 2nd slab 100% COMPLETED
  • Pouring concrete for vertical structure for first part of 2nd slab 100% COMPLETED
  • Shuttering for third slab 100% COMPLETED
  • Steel fixing for third slab 100% COMPLETED
  • Post tensioning works of 3st slab 100% COMPLETED

March 2015

  • Steel Fixing of 1st slab
  • Post tensioning works of 1st slab
  • Mechanical, electrical and plumbing works 1st slab.
  • Concrete Pouring of 1st slab
  • Steel fixing of vertical structure for first part of 2nd slab
  • Pouring concrete for vertical structure for first part of 2nd slab

February 2015

  • Steel fixing, shuttering and concrete pouring of the slab of ground water tank (ramp slab).
  • Post-tensioning works of first slab.
  • Mechanical, electrical and plumbing works of fist slab.

January 2015

  • Waterproofing works for the ground water tank (Tank Capacity is 220 m3).
  • Steel fixing, shuttering and concrete pouring of foundation and walls of ground water tank.
  • Scaffolding and shuttering of first flab (Area of slab is about 3500 m2).
  • Steel fixing of first slab.