June 2015

  • Concrete casting of 6th floor slab COMPLETED 100%
  • Mechanical, electrical and plumbing works of 6th slab 100% COMPLETED
  • Shuttering work for 7th slab 30% COMPLETED
  • Steel fixing of vertical structure for 7th floor slab completed 100%
  • Block work for 3rd floor completed 80%
  • Plaster work for 2nd floor completed 70%


May 2015

  • Shuttering work for 4th slab
  • Steel fixing for 4th slab
  • Post tensioning works for 4rd slab
  • Concrete pouring of 4th slab
  • Mechanical, electrical and plumbing works of 4th slab
  • Steel fixing for vertical structures for 5th slab
  • Shuttering works for 5th slab of first part
  • Block work for Ground floor and First floor completed 40%


April 2015

  • Shuttering work for 4th slab 100% COMPLETED
  • Steel fixing for 4th slab 100% COMPLETED
  • Post tensioning works for 4th slab 100 COMPLETED
  • Concrete pouring of 4th slab 100% COMPLETED
  • Mechanical, electrical and plumbing works of 4th slab 100% COMPLETED
  • Steel fixing for 5th Slab vertical structure started
  • Block work 30% COMPLETED

March 2015

  • Shuttering work for 3rd slab
  • Steel fixing for 3rd slab
  • Post tensioning works for 3rd slab
  • Concrete pouring of 3rd slab
  • Mechanical, electrical and plumbing works of 3rd slab
  • Steel fixing for vertical structures for 4th slab
  • Shuttering works for 4th slab of first part

February 2015

  • Scaffolding and shuttering of the slab of ground water tank (Tank Capacity is 250 m3).
  • Steel fixing and concrete pouring of the slab of ground water tank.
  • Concrete pouring of first slab (Area of slab is about 3800 m2).
  • Steel fixing of columns, shear walls and core walls of first floor.
  • Shuttering and concrete pouring of columns, shear walls and core walls of first floor.
  • Scaffolding of second slab.

January 2015

  • Waterproofing works for the ground water tank (Tank Capacity is 250 m3).
  • Steel fixing, shuttering and concrete pouring of foundation and walls of ground water tank.
  • Scaffolding and shuttering of first flab (Area of slab is about 3800 m2).
  • Steel fixing of first slab.
  • Post-tensioning works of first slab.
  • Mechanical, electrical and plumbing works of fist slab.