Azizi Iris

Azizi Iris


Azizi Iris at Al Furjan Dubai by Azizi Developments

Updates – AZIZI IRIS

June 2015

  • Concrete casting of 5th floor slab COMPLETED 100%
  • Mechanical, electrical and plumbing works 5th slab 100% COMPLETED
  • Post tensioning works of 6th slab 100% COMPLETED
  • Shuttering for 6th slab completed 100%
  • Steel fixing for 6th slab completed 100%
  • Post tensioning works of 6th floor slab 100% COMPLETED
  • Block work for 3rd floor completed 100%
  • Plaster work for 2nd floor completed 100%


May 2015

  • Steel Fixing of 3rd slab
  • Post tensioning works of 3rd slab
  • Mechanical, electrical and plumbing works 1st slab
  • Concrete Pouring of 3rd slab
  • Steel fixing of vertical structure for first part of 4th slab
  • Pouring concrete for vertical structure for first part of 4th slab
  • Shuttering of 4th slab 80% completed


April 2015

  • Steel Fixing of 2nd slab 100% COMPLETED
  • Post tensioning works of 2st slab 100% COMPLETED
  • Mechanical, electrical and plumbing works 1st slab 100% COMPLETED
  • Concrete Pouring of 2nd slab 100% COMPLETED
  • Steel fixing of vertical structure for first part of 2nd slab 100% COMPLETED
  • Pouring concrete for vertical structure for first part of 2nd slab 100% COMPLETED
  • Shuttering for third slab 100% COMPLETED
  • Steel fixing for third slab 100% COMPLETED
  • Post tensioning works of 3rd slab 100% COMPLETED

March 2015

  • Steel Fixing of 1st slab
  • Post tensioning works of 1st slab
  • Mechanical, electrical and plumbing works 1st slab
  • Concrete Pouring of 1st slab
  • Steel fixing of vertical structure for first part of 2nd slab
  • Pouring concrete for vertical structure for first part of 2nd slab

February 2015

  • Scaffolding and shuttering of the slab of ground water tank (the ramp).
  • Steel fixing and concrete pouring of the slab of ground water tank.
  • Concrete pouring of first slab (Area of slab is about 3500 m2).
  • Steel fixing of columns, shear walls and core walls of first floor.

January 2015

  • Waterproofing works for the ground water tank (Tank Capacity is 220 m3).
  • Steel fixing, shuttering and concrete pouring of foundation and walls of ground water tank.
  • Scaffolding and shuttering of first flab (Area of slab is about 3500 m2).
  • Steel fixing of first slab.