Updates – Azizi Feirouz

June 2015

  • Concrete casting of 7th floor slab COMPLETED 100%.
  • Mechanical, electrical and plumbing works of 7th slab 100% COMPLETED.
  • Shuttering for 8th slab completed 100%.
  • Steel fixing for 8th slab completed 80%.
  • Steel fixing of vertical structure of 8th floor slab 100% COMPLETED.
  • Pouring concrete for vertical structure of 8th floor slab 100% COMPLETED.
  • Block work for 3rd floor completed 60%.
  • Plaster work first floor 30%.


May 2015

  • Shuttering work for 5th slab.
  • Steel fixing for 5th slab.
  • Post tensioning works for 5th slab.
  • Concrete pouring of 5th slab.
  • Mechanical, electrical and plumbing works of 6th slab.
  • Steel fixing of vertical structure for first part of 6th floor slab.
  • Pouring concrete for vertical structure for first part of 6th floor slab.
  • Block work for ground floor completed 60%.


April 2015

  • Shuttering work for 4th slab 100% COMPLETED.
  • Steel fixing for 4th slab 100% COMPLETED.
  • Post tensioning works for 4th slab 100% COMPLETED.
  • Concrete pouring of 4th slab 100% COMPLETED.
  • Mechanical, electrical and plumbing works of 4th slab 100% COMPLETED.
  • Steel fixing of vertical structure for first part of 4th floor slab 100% COMPLETED.
  • Pouring concrete for vertical structure for first part of 5rd floor slab 100% COMPLETED.

March 2015

  • Shuttering work for 2nd slab.
  • Steel fixing for 2nd slab.
  • Post tensioning works for 2nd slab.
  • Concrete pouring of 2nd slab.
  • Mechanical, electrical and plumbing works of 2nd slab.
  • Steel fixing of vertical structure for first part of 3rd floor slab.
  • Pouring concrete for vertical structure for first part of 3rd floor slab.

February 2015

  • Concrete pouring of parking ramp (slab of ground water tank).
  • Steel fixing of 2nd part of first slab.
  • Post-tensioning works of 2nd part of first slab.
  • Mechanical, electrical and plumbing works 2nd part of fist slab.
  • Concrete pouring of 2nd part of first slab.
  • Steel fixing, shuttering and concrete pouring of columns, shear walls and core wall of 1st floor.
  • Scaffolding and shuttering of 2nd slab.

January 2015

  • Waterproofing works for the ground water tank (Tank Capacity is 220 m3).
  • Steel fixing, shuttering and concrete pouring of foundation and walls of ground water tank.
  • Steel fixing, shuttering and concrete pouring of parking ramp (slab of ground water tank).
  • Scaffolding and shuttering of first slab (Area of slab is about 3500 m2).
  • Steel fixing of first slab.
  • Post-tensioning works of first slab.
  • Mechanical, electrical and plumbing works of fist slab.
  • Concrete pouring of first pour of first slab.